[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-383997":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},383997,165,1,"单选题","以下不属于项目可行性研究内容的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投资必要性",false,{"key":16,"text":17,"correct":14},"B","财务可行性",{"key":19,"text":20,"correct":14},"C","经济可行性",{"key":22,"text":23,"correct":24},"D","自然因素及对策",true,"本题考查项目可行性研究内容。 本题考查项目可行性研究内容包括： （1）投资必要性 （2）技术可行性 （3）财务可行性 （4）组织可行性 （5）经济可行性 （6）社会可行性 （7）风险因素可行性 故本题答案选择D。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]