[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-383990":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},383990,165,1,"单选题","以下关于项目目标的说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目目标包括成果性目标和约束性目标。",false,{"key":16,"text":17,"correct":14},"B","项目目标有不同的优先级。",{"key":19,"text":20,"correct":14},"C","项目目标具有层次性。",{"key":22,"text":23,"correct":24},"D","项目目标冲突仅限于质量、成本和进度三个基本目标。",true,"本题考查项目目标的概念及特性。 项目目标的冲突不仅限于三个基本目标，有时项目的总目标体系之间也会难以协调。所以D选项错误。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]