[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382472":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},382472,164,1,"单选题","以下关于甘特图的描述中，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","直观地表明任务计划在什么时候进行",false,{"key":16,"text":17,"correct":14},"B","表明实际进展与计划要求的对比",{"key":19,"text":20,"correct":14},"C","表明子任务之间的并行和串行关系",{"key":22,"text":23,"correct":24},"D","清晰地描述任务之间的依赖关系",true,"甘特图内在思想简单，基本是一条线条图，横轴表示时间，纵轴表示活动，线条表示在整个期间上计划和实际的活动完成情况。它直观地表明任务计划在什么时候进行，及实际进展与计划要求的对比；也可以表示子任务之间的并行和串行关系。管理者由此极为便利地弄清一项任务还剩下哪些工作要做，并可以评估工作进度。但是甘特图不能清晰地描述任务之间的依赖关系，也不能清晰地指出关键任务在哪里。答案：D",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]