[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382431":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},382431,164,1,"单选题","下图是一个网络工程使用的PERT图，则该工程的关键路径是（请作答此空）；整个项目的最短工期为（ ）；在不延误项目总工期的情况下，任务G最多可以推迟开始的时间是（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","ABEFGH",false,{"key":16,"text":17,"correct":18},"B","ABEGH",true,{"key":20,"text":21,"correct":14},"C","ABDFH",{"key":23,"text":24,"correct":14},"D","ABDFGH","根据关键路径的定义可知，最长的路径就是关键路径，因此图中任务流ACEGH的持续时间是5+3+10+4=22，其余的路径依此类推，可分别得到任务流ABEGH的持续时间是25，ABEFGH的持续时间是24，ABEFH的持续时间是18，ABDFGH的持续时间是23，ABDFH的持续时间是17。所以项目关键路径长度为25，也就是整个项目的最短工期了，关键路径就是ABEGH。路径ABEGH是关键路径，因此G在关键路径上，G可以推迟的时间为0.",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]