[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382425":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},382425,164,1,"单选题","图4是一个软件项目的活动图，其中顶点表示项目里程碑，边表示包含的活动，边上的权重表示活动的持续时间，则里程碑（ ）在关键路径上。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","从开始顶点到结束顶点的最长路径为关健路径（临界路径），关键路径上的活动为关键活动。在本题中找出的最长路径是Start→2→5→7→8→Finish，其长度为8+15+15+7+20=65，而其它任何路径的长度都比这条路径小，因此我们可以知道里程碑2在关键路径上。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]