[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382414":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},382414,164,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，边上的数字表示活动的持续时间(天)，则完成该项目的最少时间为（ ）天。活动FG的松驰时间为( 本题)天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","9",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":21},"C","18",true,{"key":23,"text":24,"correct":14},"D","26","关键路径是ADFHJ=10+8+18+10=46.FG中F在关键路径上，因此FG最早完成时间是18+3=21.最晚完成时间为：46-7=39.因此松弛时间为39-21=18天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]