[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382410":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},382410,164,1,"单选题","进度安排的常用图形描述方法有GANTT图和PERT图。GANTT图不能清晰地描述（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","每个任务从何时开始",false,{"key":16,"text":17,"correct":14},"B","每个任务到何时结束",{"key":19,"text":20,"correct":14},"C","每个任务的进展情况",{"key":22,"text":23,"correct":24},"D","各任务之间的依赖关系",true,"甘特图的优点是直观表明各个任务的计划进度和当前进度，能动态地反映软件开发进展的情况，是小型项目中常用的工具。缺点是不能显式地描绘各个任务间的依赖关系，关键任务也不明确。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]