[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382407":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},382407,164,1,"单选题","某项目主要由A～I任务构成，其计划图（如下图所示）展示了各任务之间的前后关系以及每个任务的工期（单位：天），该项目的关键路径是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","A→G→I",false,{"key":16,"text":17,"correct":14},"B","A→D→F→H→I",{"key":19,"text":20,"correct":21},"C","B→E→G→I",true,{"key":23,"text":24,"correct":14},"D","C→F→H→I","关键路径是时间最长的那条路径，B→E→G→I这条路径耗时最长，总共2+5+6+7=20天。 经过任务A的时间最长路径是A→D→F→H→I，总共2+4+1+4+7=18天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]