[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382380":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},382380,164,1,"单选题","若一个项目的计划图（如下图所示） ，则完成项目所需要的最短时间是 （请作答此空）天。活动G对多推迟（ ）天完工，不会影响项目的完工日期。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","16",false,{"key":16,"text":17,"correct":14},"B","17",{"key":19,"text":20,"correct":14},"C","18",{"key":22,"text":23,"correct":24},"D","19",true,"最长时间的那个路径就是关键路径。显然本题中是A→B→C→D→I，CPM=3+2+2+7+5=19.由于活动G不在关键路径上，因此其最早完工时间为12天，在不影响I活动的 结束时间前提下，最迟完工时间为14天。因此最多推迟2天完工不会影响总工期。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]