[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382376":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},382376,164,1,"单选题","下图为某系统集成项目的网络工程计划图，从图可知项目最短工期为（ ）天，至少需要投入（请作答此空）人才能完成该项目（假设每个技术人员均能胜任每项工作）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","6",true,{"key":23,"text":24,"correct":14},"D","8","主机安装需要2人2天，广域网络安装需要2人3天，合起来正好是2人5天。再结合上局域网络安装的4人5天，总共是6人5天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]