[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382371":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},382371,164,1,"单选题","若一个项目的计划图（如下图所示） ，则完成项目所需要的最短时间是（ ）天。活动G对多推迟（请作答此空）天完工，不会影响项目的完工日期。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","最长时间的那个路径就是关键路径。显然本题中是A→B→C→D→I，CPM=3+2+2+7+5=19.由于活动G不在关键路径上，因此其最早完工时间为12天，在不影响I活动的 结束时间前提下，最迟完工时间为14天。因此最多推迟2天完工不会影响总工期。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]