[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382356":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},382356,164,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，边上的数字表示活动的持续时间(天)，则完成该项目的最少时间为( )天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","37",{"key":19,"text":20,"correct":14},"C","38",{"key":22,"text":23,"correct":24},"D","46",true,"关键路径是ADFHJ=10+8+18+10=46.",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]