[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382349":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},382349,164,1,"单选题","某工程网络计划如图1所示（单位：天），该工程的总工期为（ ）天，工作D的自由时差是（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","17；2",false,{"key":16,"text":17,"correct":14},"B","19；2",{"key":19,"text":20,"correct":21},"C","20；2",true,{"key":23,"text":24,"correct":14},"D","22；2","工程网络计划计算关键路径为：ACEG，总工期（最长路径）为20天；D的自由时差2天，D工期延长至5天也不影响总工期。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]