[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382339":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},382339,164,1,"单选题","下图是一个软件项目的活动图，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，则里程碑（ ）在关键路径上，活动FG的松弛时间为（请作答此空）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","19",false,{"key":16,"text":17,"correct":18},"B","20",true,{"key":20,"text":21,"correct":14},"C","21",{"key":23,"text":24,"correct":14},"D","24","关键路径法（Critical Path Method，CPM），在一个项目中，只有项目网络中最长的或耗时最多的活动完成之后，项目才能结束，这条最长的活动路线就叫关键路径，组成关键路径的活动称为关键活动。在本题中开始-D-F-H-结束是关键路径。里程碑D在关键路径上松弛时间是不影响完工前提下可能被推迟完成的最大时间，而对于活动FG的松弛时间为开始-D-F-H-结束的时间减去开始-D-F-G-结束的时间=48-28=20，最多能推迟20天进行。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]