[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382328":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},382328,164,1,"单选题","下图为某工程进度网络图， 结点1为起点，结点11为终点，那么关键路径为（ ），此工程最快（请作答此空）天完成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","18",false,{"key":16,"text":17,"correct":18},"B","28",true,{"key":20,"text":21,"correct":14},"C","22",{"key":23,"text":24,"correct":14},"D","20","关键路径为最长的路径，对比四个选项，路径1-3-5-8-9-10-11最长,值为28。因此完成此工程的最短时间（最快完成）就是28.",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]