[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382230":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},382230,164,1,"单选题","设某一个任务需要8个加工部件加上才能完成．每个加工部件加工需要时间为T，现采用流水线加工方式，完成100个任务。共需要（ ）时间。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","8T",false,{"key":16,"text":17,"correct":14},"B","100T",{"key":19,"text":20,"correct":14},"C","108T",{"key":22,"text":23,"correct":24},"D","107T",true,"所需时间为8T+（100-1）T=107T。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 网络工程师","职业资格",0]