[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382029":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},382029,163,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，边上的数字表示活动的持续时间（天），活动BD和HK最早可以从第（ ）天开始。（活动A B、AE和AC最早从第1天开始）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","17",false,{"key":16,"text":17,"correct":14},"B","18",{"key":19,"text":20,"correct":14},"C","19",{"key":22,"text":23,"correct":24},"D","20",true,"关键路径：在活动图中时间跨度最长的路径。其决定项目最少工期。项目关键路径是路径最长的一条，在该图中路径：A→B→D→I→J→L=3+5+2+2+8=20，是路径最长的一条。有任务A→B需要3天，所以B→D应在第4天开始；由于H点最迟出的时间为10后（A→E→G→H），所以H→K应在第11天开始",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 数据库系统工程师","职业资格",0]