[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382017":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},382017,163,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，边上的数字表示活动的持续天数，则完成该项目的最少时间为（ ）天。活动EH和IJ的松弛时间分别为（请作答此空）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3和3",false,{"key":16,"text":17,"correct":14},"B","3和6",{"key":19,"text":20,"correct":21},"C","5和3",true,{"key":23,"text":24,"correct":14},"D","5和6","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 数据库系统工程师","职业资格",0]