[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382013":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},382013,163,1,"单选题","某项目包含的活动如下表所示，完成整个项目的最短时间为（请作答此空）周。不能通过缩短活动（ ）的工期，来缩短整个项目的完成时间。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","16",false,{"key":16,"text":17,"correct":14},"B","17",{"key":19,"text":20,"correct":14},"C","18",{"key":22,"text":23,"correct":24},"D","19",true,"本题考査软件项目管理的基础知识。活动图是描述一个项目中各个工作任务相互依赖关系的一种模型，项目的很多重要特性可以通过分析活动图得到，如估算项目完成时间，计算关键路径和关键活动等。根据上表给出的数据，构建活动图，如下图所示。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 数据库系统工程师","职业资格",0]