[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-382002":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},382002,163,1,"单选题","（ ）软件成本估算模型是一种静态单变量模型，用于对整个软件系统进行估算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Putnam",false,{"key":16,"text":17,"correct":18},"B","基本COCOMO",true,{"key":20,"text":21,"correct":14},"C","中级COCOMO",{"key":23,"text":24,"correct":14},"D","详细COCOMO","本题考査软件项目管理的基础知识。Putnam和COCOMO都是软件成本估算模型。Putnam模型是一种动态多变量模型，假设在软件开发的整个生存期中工作量有特定的分布。结构性成本模型COCOMO模型分为基本COCOMO模型、中级COCOMO模型和详细COCOMO。基本COCOMO模型是一个静态单变量模型，对整个软件系统进行估算：中级COCOMO模型是一个静态多变模型，将软件系统模型分为系统和部件两个层次，系统由部件构成；详细COCOMO模型将软件系统模型分为系统、子系统和模块三个层次，除了包括中级模型所考虑的因素外，还考虑了在需求分析、软件设计等每一步的成本驱动属性的影响。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 数据库系统工程师","职业资格",0]