[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-381557":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},381557,162,1,"单选题","某项目包含的活动如下表所示，完成整个项目的最短时间为（17）周。不能通过缩短活动（18）的工期，来缩短整个项目的完成时间。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","16",false,{"key":16,"text":17,"correct":14},"B","17",{"key":19,"text":20,"correct":14},"C","18",{"key":22,"text":23,"correct":24},"D","19",true,"本题考查软件工程进度管理知识点根据题目中表格内容可画出下图所示的PERT图（S表示开始节点，H表示终节点） 根据上图可得关键路径为：A、D、E、F、H，长度 19，所以最短工期19周由于B不是关键路径上的活动，所以压缩他，无法缩短整个项目的完成时间",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 软件设计师","职业资格",0]