[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-381525":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},381525,162,1,"单选题","某公司要开发一个软件产品，产品的某些需求是明确的，而某些需求则需要进一步细化。由于市场竞争的压力，产品需要尽快上市，则开发该软件产品最不适合采用（ ）模型",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","瀑布",true,{"key":16,"text":17,"correct":18},"B","原型",false,{"key":20,"text":21,"correct":18},"C","增量",{"key":23,"text":24,"correct":18},"D","螺旋","瀑布模型将软件生命周期划分为需求分析、软件设计、程序编写、软件测试和运行维护等基本活动，并且规定了它们自上而下、相互衔接的固定次序，如同瀑布流水，逐级下落瀑布模型要求待开发的系统需求是完整的、简明的、一致的，其突出的缺点是不适应用户需求的变化，开发模型是线性的，用户只有等到整个过程的末期才能见到开发成果对于需求不确定的软件产品不适合采用瀑布模型",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 软件设计师","职业资格",0]