[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-381461":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":15,"analysis":22},381461,162,1,"单选题","某项目包含的活动如下表所示，完成整个项目的最短时间为（ ）周。不能通过缩短活动（ ）的工期，来缩短整个项目的完成时间",[11,14,17,20],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":16},"B",true,{"key":18,"text":19,"correct":13},"C","D",{"key":19,"text":21,"correct":13},"F","本题考查软件工程进度管理知识点。根据题目中表格内容可画出下图所示的PERT图（S表示开始节点，H表示终节点）。 根据上图可得关键路径为：A、D、E、F、H，长度 19，所以最短工期19周。由于B不是关键路径上的活动，所以压缩他，无法缩短整个项目的完成时间。",{"id":6,"name":24,"category":25,"favorite":26},"(中级) 软件设计师","职业资格",0]