[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-381449":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},381449,162,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，连接顶点的边表示活动，边上的数字表示活动所需的天数，则完成该项目的最少时间为（ ）天",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","9",false,{"key":16,"text":17,"correct":14},"B","15",{"key":19,"text":20,"correct":14},"C","22",{"key":22,"text":23,"correct":24},"D","24",true,"关键路径为ABCEFIKL=24天，即项目完成最少要24天",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 软件设计师","职业资格",0]