[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-381448":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},381448,162,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，连接顶点的边表示活动，边上的数字表示活动所需的天数，活动BD最多可以晚（ ）天开始而不会影响整个项目的进度",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","5",{"key":23,"text":24,"correct":18},"D","9","关键路径为ABCEFIKL=24天，即项目完成最少要24天。BD活动的最早时间为2，最迟时间为4，总时差=最迟时间-最早时间=2天，即BD最多可以晚2天而不影响整个项目进度",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 软件设计师","职业资格",0]