[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-381440":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},381440,162,1,"单选题","",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3和10",false,{"key":16,"text":17,"correct":18},"B","4和11",true,{"key":20,"text":21,"correct":14},"C","3和9",{"key":23,"text":24,"correct":14},"D","4和10","项目的工期是从开始到结束持续时间最长的工作。题目中持续时间最长的是ABDIJL，需要时间20 天。 BD 活动在AB 活动结束之后便可以开始，所以最早开始时间为 4。HK 活动需要在AEGH与ACFH 两条路径上的活动均完成之后，才能开始，所以最早开始时间为 11。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 软件设计师","职业资格",0]