[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-381384":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},381384,162,1,"单选题","",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","17",false,{"key":16,"text":17,"correct":14},"B","18",{"key":19,"text":20,"correct":14},"C","19",{"key":22,"text":23,"correct":24},"D","20",true,"项目的工期是从开始到结束持续时间最长的工作。题目中持续时间最长的是AEGHKL，需要时间20天。 BD活动在AB活动结束之后便可以开始，所以最早开始时间为3。HK活动需要在AEGH与ACFH两条路径上的活动均完成之后，才能开始，所以最早开始时间为10",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 软件设计师","职业资格",0]