[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-381371":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},381371,162,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，边上的数字表示相应活动的持续时间（天），活动BC和BF最多可以晚开始（ ）天而不会影响整个项目的进度",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0和7",true,{"key":16,"text":17,"correct":18},"B","0和11",false,{"key":20,"text":21,"correct":18},"C","2和7",{"key":23,"text":24,"correct":18},"D","2和11","BC和BF最晚开始的时间可以分别为0天和7天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 软件设计师","职业资格",0]