[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-381204":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":23},381204,161,1,"单选题","下图是一个软件项目的活动图，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，则里程碑（请作答此空）在关键路径上。活动GH的松弛时间是（ ）。",[11,15,18,20],{"key":12,"text":13,"correct":14},"A","B",true,{"key":13,"text":16,"correct":17},"E",false,{"key":19,"text":19,"correct":17},"C",{"key":21,"text":22,"correct":17},"D","K","本题考查活动图的基础知识。 根据关键路径法，计算出关键路径为A-B-D-I-J-L，其长度为20。因此里程碑B在关键路径上，而里程碑E、C和K不在关键路径上。包含活动GH的最长路径是A-E-G-H-K-L，长度为17，因此该活动的松弛时间为20-17=3。",{"id":6,"name":25,"category":26,"favorite":27},"(中级) 软件评测师","职业资格",0]