[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-381202":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},381202,161,1,"单选题","下图是一个软件项目的活动图，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，则里程碑（ ）没有按时完成会影响整个项目的进度。若活动0→2完成后，停止3天才开始活动2→6，则完成整个项目的最少时间是（请作答此空）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","53",false,{"key":16,"text":17,"correct":14},"B","55",{"key":19,"text":20,"correct":21},"C","56",true,{"key":23,"text":24,"correct":14},"D","57","本题考查软件项目管理的基础知识。根据关键路径法，计算出关键路径为0-2-5-7-8-9，关键路径长度为55。因此里程碑2在关键路径上，而里程碑1、3和4不在关键路径上。若活动0→2完成后，停止3天才开始活动2→6，则相当于0-2-6-9是一个关键路径，此时，完成项目的最短时间应该是56天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 软件评测师","职业资格",0]