[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-381201":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},381201,161,1,"单选题","以下关于项目估算的叙述中，不正确的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在项目估算中，需要估算的项目量参数包括项目规模、开发软件所需的工作量、项目持续时间和成本",false,{"key":16,"text":17,"correct":14},"B","由于专家判断受到差异性和主观性的影响，以及对当前数据依赖性的影响，用专家判断方法进行项目估计会得到不精确的估算值",{"key":19,"text":20,"correct":21},"C","由于启发式估算方法，如COCOMOII模型具有严谨的估算形式，因此可以得到精确的估算值",true,{"key":23,"text":24,"correct":14},"D","项目估算是制定项目开发计划的基础和依据","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 软件评测师","职业资格",0]