[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-380541":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":23},380541,161,1,"单选题","下图是一个软件项目的活动图，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，则里程碑（请作答此空）在关键路径上。活动GH的松弛时间是（ ）。",[11,15,18,20],{"key":12,"text":13,"correct":14},"A","B",true,{"key":13,"text":16,"correct":17},"E",false,{"key":19,"text":19,"correct":17},"C",{"key":21,"text":22,"correct":17},"D","K","项目关键路径是路径最长的一条，在该图中路径：A->B->D->I->J->L=3+5+2+2+8=20，是路径最长的一条。故第一问正确答案为A。松弛时间是在不影响项目进度的前提下，可推迟开始的时间。本题中项目关键路径的时间是20，G、H所在的路径A->E->G->H->K->L=4+3+3+4+3=17，20-17=3，即GH的松弛时间为3。故第二问正确答案为D。",{"id":6,"name":25,"category":26,"favorite":27},"(中级) 软件评测师","职业资格",0]