[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-376745":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},376745,157,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，边上的数字表示活动的持续时间（天），则完成该项目的最少时间为（请作答此空）天。活动BD最多可以晚开始（ ）天而不会影响整个项目的进度。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":14},"B","21",{"key":19,"text":20,"correct":21},"C","22",true,{"key":23,"text":24,"correct":14},"D","24","先找出关键路径为：ABDGIKL，其长度为22，所以最短工期22天。BD是关键路径上的活动，其总时差为0，不能耽搁，所以BD最多延误0天不会影响总工期。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)程序员","职业资格",0]