[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-376722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},376722,157,1,"单选题","估计一个项目所需时间常有乐观估计时间、最可能时间和悲观估计时间。根据这三个时间的加权平均(权为常数)可以推算出这个项目的期望时间。下表中，项目3的期望时间大致是( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6.2",false,{"key":16,"text":17,"correct":18},"B","6.5",true,{"key":20,"text":21,"correct":14},"C","6.6",{"key":23,"text":24,"correct":14},"D","6.7","本题考查数学应用(线性方程组求解)基本能力。 设计算期望时间的三个权分别为a、b、c，其中a+b+c=1，即 期望时间=a*乐观估计+b*最可能估计+c*悲观估计 由题中的项目1和2可知：a+3b+11c=4，a+1.5b+14c=3.5，由于a+b+c=1，所以a=1\u002F6，b=4\u002F6，c=1\u002F6。从而，项目3的期望时间为3\u002F6+6.25*4\u002F6+11\u002F6=6.5。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)程序员","职业资格",0]