[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-376679":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},376679,157,1,"单选题","一项工程完工所需的最少时间等于某个( ) 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","AOE网中源点到汇点事件最多的路径的长度",false,{"key":16,"text":17,"correct":18},"B","AOE网中源点到汇点的最长路径的长度",true,{"key":20,"text":21,"correct":14},"C","AOE网中源点到汇点的最短路径的长度",{"key":23,"text":24,"correct":14},"D","AOE网中源点到汇点活动最多的路径的长度","本题考查AOE网的知识。AOE网是用顶点表示活动，用边表示活动间的优先关系的有向图。在AOE网中，有些活动可以并行地进行，完成工程所需的最少时间是从开始点到完成点的最长路径，即关键路径。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)程序员","职业资格",0]