[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-376670":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},376670,157,1,"单选题","某项目计划 20 天完成，花费 4 万元。在项目开始后的前 10 天内遇到了偶发事件，到第 10 天末进行中期检查时，发现己花费 2 万元，但只完成了 40%的工作量。如果此后不发生偶发事件，则该项目将（63）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","推迟 2 天完工，不需要增加费用",false,{"key":16,"text":17,"correct":18},"B","推迟 2 天完工，需要增加费用 4000 元",true,{"key":20,"text":21,"correct":14},"C","推迟 5 天完工，不需要增加费用",{"key":23,"text":24,"correct":14},"D","推迟 5 天完工，需要增加费用 1 万元","工作量为1，正常速度为1\u002F20，现在还剩0.6，因此还需要0.6\u002F1\u002F20=12天，因此要推迟2天完工。正常花费为4，现在还有60%未完成，因此还需要0.6*4=2.4万元，因此需要增加费用4000元。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)程序员","职业资格",0]