[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-375562":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},375562,153,2,"多选题","以下关于制定劳动定额方法的表述，正确的是（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","经验估工法程序复杂，工作量大",false,{"key":16,"text":17,"correct":14},"B","经验估工法制定定额准确性较好",{"key":19,"text":20,"correct":21},"C","类推比较法简便易行，工作量小",true,{"key":23,"text":24,"correct":21},"D","技术定额法需要采用分析计算的方法",{"key":26,"text":27,"correct":21},"E","技术定额法是比较先进和科学的方法","CDE","AB两项，经验估工法简便易行，工作量小，能满足定额制定“快”和“全”的要求；容易受估工人员的水平和经验的局限，出现定额偏高、偏低的现象，制定的劳动定额准确性较差，定额水平不易平衡。C项，类推比较法制定定额简便易行，工作量小，便于保持定额水平的平衡，也有利于提高定额的准确性。DE两项，技术定额法是通过对生产技术条件的分析，在挖掘生产潜力以及操作合理化的基础上，采用分析计算或实地测定来制定定额的方法，是一种比较先进和科学的方法。",{"id":6,"name":31,"category":32,"favorite":33},"四级(理论知识、专业能力)","职业资格",0]