[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-375544":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},375544,153,1,"单选题","定额时间中最主要的组成部分是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","作业时间",true,{"key":16,"text":17,"correct":18},"B","作业宽放时间",false,{"key":20,"text":21,"correct":18},"C","个人需要与休息宽放时间",{"key":23,"text":24,"correct":18},"D","准备与结束时间","作业时间是指直接用于完成生产作业或零件加工所消耗的时间。它是定额时间中最主要的组成部分。",{"id":6,"name":27,"category":28,"favorite":29},"四级(理论知识、专业能力)","职业资格",0]