[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-373667":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},373667,153,2,"多选题","(2019年5月)非定额时间包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","准备与结束时间",false,{"key":16,"text":17,"correct":18},"B","非个人造成的停工时间",true,{"key":20,"text":21,"correct":18},"C","个人造成的非生产时间",{"key":23,"text":24,"correct":18},"D","非个人造成的非生产时间",{"key":26,"text":27,"correct":18},"E","个人造成的停工时间","BCDE","非定额时间包括非个人造成的停工时间、个人造成的停工时间、个人造成的非生产时间、非个人造成的非生产时间。",{"id":6,"name":31,"category":32,"favorite":33},"四级(理论知识、专业能力)","职业资格",0]