[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-373011":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},373011,152,1,"单选题","（ ）是指在计划期内所要执行的劳动定额提高的幅度。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","定额控制数",false,{"key":16,"text":17,"correct":14},"B","定额完成系数",{"key":19,"text":20,"correct":14},"C","定额计划数量系数",{"key":22,"text":23,"correct":24},"D","计划定额完成系数",true,"有些企业采用计划定额完成系数来确定修改定额的控制数。计划定额完成系数是指在计划期内所要执行的劳动定额提高的幅度。由于工时定额与产量定额成倒数关系，因此： 计划产量定额=现行产量定额×计划定额完成系数。 故选D",{"id":6,"name":27,"category":28,"favorite":29},"三级(理论知识、专业能力)","职业资格",0]