[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-373009":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},373009,152,1,"单选题","（ ）是指依据时间定额标准制定的工时，在衡量企业现行定额水平时，应选择经过国家有关部门正式颁布或批准的时间定额标准作依据。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实测工时",false,{"key":16,"text":17,"correct":14},"B","实耗工时",{"key":19,"text":20,"correct":21},"C","标准工时",true,{"key":23,"text":24,"correct":14},"D","标准差","标准工时是指依据时间定额标准制定的工时，在衡量企业现行定额水平时，应选择经过国家有关部门正式颁布或批准的时间定额标准作依据。该方法由于衡量标准客观，反映现行定额的状况比较真实，不同企业（或车间）采用同一时间定额标准来衡量，还能反映出企业之间以及企业内部定额水平的高低及先进程度。它的缺点是工作量大，也只能有重点地选择若干典型的、关键的工序或零件来进行。 故选C。",{"id":6,"name":27,"category":28,"favorite":29},"三级(理论知识、专业能力)","职业资格",0]