[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-372957":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},372957,152,2,"多选题","可采用（ ）方法对生产工人加工产品的实耗工时，以及整个工作班、工作时间消耗进行直接观察。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作日计时",false,{"key":16,"text":17,"correct":18},"B","工作日写实",true,{"key":20,"text":21,"correct":18},"C","测时",{"key":23,"text":24,"correct":14},"D","现场观察",{"key":26,"text":27,"correct":18},"E","瞬间观察法","BCE","以原始记录为根据的产品实耗工时统计，往往受到填写者人为因素的影响，存在一定的登记性误差，使统计资料的准确性得不到切实的保证，特别是对于生产工人实际操作情况，以及各种时间的支配、利用的合理性，缺乏全面的了解。为了确切掌握生产工人工作时间的支配情况，使制定和修订出的新定额达到先进合理的要求，还必须采用以下几种方法，对生产工人加工产品的实耗工时，以及整个工作班、工作时间消耗进行直接观察: 1．工作日写实。 2．测时。 3．瞬间观察法。 故选B,C,E。",{"id":6,"name":31,"category":32,"favorite":33},"三级(理论知识、专业能力)","职业资格",0]