[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-368691":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},368691,151,1,"单选题","（2018年11月）在培训结束时，对受训者的学习效果和培训项目本身的有效性所进行的评估是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设性评估",false,{"key":16,"text":17,"correct":14},"B","正式评估",{"key":19,"text":20,"correct":21},"C","总结性评估",true,{"key":23,"text":24,"correct":14},"D","非正式评估","建设性评估就是在培训过程中以改进而不是以是否保留培训项目为目的的评估。总结性评估是指在培训结束时，对受训者的学习效果和培训项目本身的有效性所进行的评估。这种评估经常是正式的和客观的。非正式评估是指评估者依据自己的主观性的判断，而不是用事实和数字来加以证明。",{"id":6,"name":27,"category":28,"favorite":29},"二级(理论、专业、综合评审)","职业资格",0]