[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-360696":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},360696,145,2,"多选题","成本法估价中的房地产开发成本有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","勘察设计和前期工程费",true,{"key":16,"text":17,"correct":18},"B","管理费用",false,{"key":20,"text":21,"correct":14},"C","基础设施建设费",{"key":23,"text":24,"correct":14},"D","房屋建筑安装工程费",{"key":26,"text":27,"correct":14},"E","公共配套设施建设费","ACDE","开发成本主要包括：①勘察设计和前期工程费；②基础设施建设费；③房屋建筑安装工程费；④公共配套设施建设费；⑤开发建设过程中的税费。",{"id":6,"name":31,"category":32,"favorite":33},"专业基础","职业资格",0]