[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-359910":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},359910,145,1,"单选题","投资回收期是指以项目的净收益抵偿全部（ ）所需要的时间。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","现金流入",false,{"key":16,"text":17,"correct":18},"B","初始投资",true,{"key":20,"text":21,"correct":14},"C","净现金流量",{"key":23,"text":24,"correct":14},"D","运营费用","静态投资回收期是指在不考虑资金的时间价值时，以投资项目的净现金流量抵偿原始总投资所需要的时间，或者说以净收益收回初始投资所需要的时间。动态投资回收期是把投资项目各期（通常以年为单位）的净现金流量按基准收益率或目标收益率折现之后，再来计算投资回收期的。",{"id":6,"name":27,"category":28,"favorite":29},"专业基础","职业资格",0]