[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-349884":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},349884,141,3,"判断题","在工程实施过程中，根据工程实际情况和客观条件的变化，可随时调整网络计划，使得计划永远处于最切合实际的最佳状态，保证该项工程以最小的消耗，取得最大的经济效益。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"考点:进度控制。在工程实施过程中，根据工程实际情况和客观条件的变化，可随时调整网络计划，使得计划永远处于最切合实际的最佳状态，保证该项工程以最小的消耗，取得最大的经济效益。",{"id":6,"name":21,"category":22,"favorite":23},"开发经营与管理","职业资格",0]