[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-349760":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},349760,141,2,"多选题","房地产开发项目可行性研究中开发建设计划的主要内容有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","前期开发计划",true,{"key":16,"text":17,"correct":14},"B","工程建设计划",{"key":19,"text":20,"correct":21},"C","物业服务计划",false,{"key":23,"text":24,"correct":14},"D","建设场地布置",{"key":26,"text":27,"correct":14},"E","施工队伍选择","ABDE","本题考查的是可行性研究的内容。开发建设计划的编制：（1）前期开发计划，包括从项目创意、可行性研究、获取土地使用权、委托规划设计、取得开工许可证直至完成开工前准备等一系列工作计划；（2）工程建设计划，包括各个单项工程的开、竣工时间，进度安排，市政工程的配套建设计划等；（3）建设场地的布置；（4）施工队伍的选择。",{"id":6,"name":31,"category":32,"favorite":33},"开发经营与管理","职业资格",0]