[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-349750":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},349750,141,2,"多选题","由于施工工期延长，开发商要承担的风险有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","使项目的规模.布局发生变化",false,{"key":16,"text":17,"correct":18},"B","承担更多的贷款利息",true,{"key":20,"text":21,"correct":18},"C","增加房地产开发项目的融资成本",{"key":23,"text":24,"correct":18},"D","承担总费用上涨的风险",{"key":26,"text":27,"correct":14},"E","租售期延长","BCD","本题考查的是房地产开发项目的主要不确定性因素。如果施工工期延长，开发商一方面要承担更多的贷款利息，另一方面还要承担总费用上涨的风险。另外，承包合同形式选择不当也可能导致承包商有意拖延工期，致使项目开发期延长。",{"id":6,"name":31,"category":32,"favorite":33},"开发经营与管理","职业资格",0]