[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-349653":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},349653,141,2,"多选题","(2017年真题) 房地产开发项目竣工后，建设单位移交给城市档案馆的技术资料主要有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","前期工作资料",true,{"key":16,"text":17,"correct":14},"B","土建资料",{"key":19,"text":20,"correct":14},"C","安装资料",{"key":22,"text":23,"correct":24},"D","租售资料",false,{"key":26,"text":27,"correct":24},"E","物业管理资料","ABC","本题考查的是竣工验收。编制竣工档案时，技术资料包括前期工作资料、土建资料和安装资料。",{"id":6,"name":31,"category":32,"favorite":33},"开发经营与管理","职业资格",0]