[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-349583":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},349583,141,2,"多选题","对于“开发－销售”模式下的房地产投资项目，分析其动态盈利能力时的计算期包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","开发期",true,{"key":16,"text":17,"correct":18},"B","论证决策期",false,{"key":20,"text":21,"correct":18},"C","经营准备期",{"key":23,"text":24,"correct":18},"D","经营期",{"key":26,"text":27,"correct":14},"E","销售期","AE","本题考查的是净现值。开发销售型的计算期为开发期加上销售期。",{"id":6,"name":31,"category":32,"favorite":33},"开发经营与管理","职业资格",0]